Quick Links
Skip to main contentSkip to navigation
Main Navigation

Tour of New Construction 08-30-2014

Here is a video tour of construction as of August 30, 2014 at Salisbury High School.  (Note: This is the same video as is posted on the Salisbury R-IV School District Facebook page except this video has a few seconds of video at the . . .

read more...

Construction Photos

Click on the picture to see a slide show of pictures from inside the dome from the past several weeks and to see pictures of the start of the lobby/theater walls.  The dome contractor anticipates completing the structure by April 1. . . .

read more...

Construction Update 1-17-14

It was anticipated the dome would be inflated this week or early next week.  However, the strong winds yesterday caused damage to the roof membrane.  This has put a halt on the roofing structure for the dome.  Pictures show . . .

read more...

Construction Work Continues 12-3-2013

Construction work is continuing on the FEMA shelter and theater/lobby area.  The block walls of the dome are being installed as well as footings in the theater/lobby area.  Click on picture to see additional recent pictures of the . . .

read more...

Masonry Work Has Begun

The masons have been on site and block walls are now coming up out of the ground.  They are making visible progress daily.  Click on the picture to see several more pictures from the week of November 11-15, 2013.

read more...

Construction Work Continues 10-11-2013

All of the fill material has been brought in and compacted.  Rammed aggregate piers are now being put in the ground.  The pictures show the end of the site prep, the mobilization of the pier contractor, and pier installation.

read more...

Construction Work Continues 10-1-13

Click Picture for Slide Show

Recent construction work has included removal of unsuitable soil, hauling in, leveling, and compacting suitable material, removal of trees and sign, and some demolition.   Memorial stones and bench were removed prior to . . .

read more...

Construction Work Has Begun on FEMA Safe Room

Dirt Work Started 9-19-2013

Thursday, September 19, the first dirt was pushed on the site of the new FEMA Safe Room and Multi-Purpose Area.  While the 19th was the first day, not much was done the 19th and workers were rained out on the 20th.  Monday, . . .

read more...

Board Awards Contracts for Building Project

On June 27, bids for the FEMA shelter and lobby/theater area were opened in the Salisbury R-IV School District Central Office.  The bids were higher than expected.  The design team began reviewing bids and possible cost saving . . .

read more...

FEMA Gives Final Approval

On Monday, April 15, the Salisbury R-IV School District received notification from FEMA it had received final approval for the construction of a tornado safe room.  In addition, the budget amendment requested by the district has also . . .

read more...

Building Update and Demolition Slide Show

The demolition of the old Salisbury High School is complete.  The district is now awaiting approval of the final building design by FEMA.  Although FEMA has already awarded a grant to the Salisbury R-IV School District for the . . .

read more...

Old Building Used for Fire and Rescue Training

Tuesday, June 26, the old high school building was used as a training ground for area fire departments and ambulance crews.  A theatrical smoke machine was used to simulate a fire.  Firefighters entered the building to fight the . . .

read more...

Old Building to be Razed

The two story section of the Salisbury High School and the old gym will be razed this summer.  Patrons of the district are welcome to walk through the old building during normal business hours through June 8.  If there are items . . .

read more...

Building Concept Approved

The Salisbury R-IV Board of Education approved a building concept during a special meeting held Monday, April 2, in the Salisbury HS Cafeteria.  The building concept includes a dome which will serve as a FEMA Tornado Safe Room and a . . .

read more...

FEMA Building Options Considered

Feedback Requested

The Salisbury Board of Education held their regular monthly meeting on Monday, March 12, 2012.  During the meeting the board reviewed and discussed several different building options which would use the grant money recently awarded to . . .

read more...

Salisbury R-IV Receives FEMA Grant

District to Construct Safe Room/Multipurpose Facility

The Salisbury R-IV School District received official word on Friday, February 10, 2012, that it had received a grant from FEMA to construct a tornado safe room.  The grant will be awarded in two phases.  Phase I will provide . . .

read more...

Central Office Project 10-18-11

When the district accepted the plans for the new high school classroom addition, that was only part of the project presented to the board.  The plan presented also included a new gym and interior renovation, including the old central . . .

read more...

2-14-2011 Building Update

The past few weeks have seen many changes in the new classroom addition.  Casework, tack boards, marker boards, doors, and ceiling tiles have been installed.  The interior is really beginning to look like a school building.  In . . .

read more...

1-28-2011 Building Update

Most of the recent work in the building has been overhead work.  The painters finished most of their work in the new addition and the focus this past week has been ceiling grid work, running electrical, installing lighting, and . . .

read more...

1-19-2011 Building Update

The inside of the new classroom addition is really starting to take shape.  Painters have been busy painting the classrooms and hallway.  Today, ceiling grid installers began putting up hangers for their grid work.  In the next . . .

read more...

1-3-2011 Building Update

Several things have been happening in the new addition.  Topping the list is new windows have been installed.  In one of the pictures, the windows are shown along with guttering being installed.  Another picture has an interior . . .

read more...

12-2-2010 Building Update

December 1 the rooftop units were installed on the new building.  Also, metal studs, insulation, and sheet rock were installed on the top of the interior brick walls.  December 3, exterior doors are to be installed. Inside, . . .

read more...

10-18-2010 Building Update

(To see additional pictures from 10-8 through 10-18-10, click on the picture of the building.) The weather the past three weeks has been beautiful and things have been changing rapidly with the new classroom addition.  The masons . . .

read more...

10-11-10 Building Update

The interior block walls are installed and steel has been put in place for the roofing system.  The next two things happening are tying the old building into the new building (on the north end of the new addition) and installing brick . . .

read more...

9-28-10 Building Update

The final exterior wall, the west wall, of the new addition is being built this week.  Once the exterior walls are finished, steel for the roof will be installed.  The roof installation is scheduled to begin October 4.  Masons . . .

read more...

9-9-10 Building Construction and Renovation Update

The concrete slab has been poured and block walls are going up.  Plumbing and electrical are being run in the block walls as they are installed.  Currently, the exterior walls are being built.  The exteriors walls will receive . . .

read more...

9-3-10 Building Construction and Renovation Update

(Click image for additional pictures)

Friday, September 3, the concrete pad was poured for the classroom addition to the high school.  The concrete started arriving at 6:00 a.m. and was poured with a pump trunk.  158 cubic yards of concrete later, the pad was poured. . . .

read more...

Building Construction and Renovation Update 8-30-10

(8-31-10 Rain has delayed concrete until 9-3-10)

Due to a delay in material, worked slowed on the building project last week.  The storm sewer was installed around the new building site.  Concrete was scheduled to be poured last week, but the new scheduled date is Tuesday, August . . .

read more...

Building Construction and Renovation Update 8-19-10

Electrical and plumbing contractors are busy burying their lines in the ground under the future high school addition.  Once the underground work is complete, hopefully the end of this week or early next week, the site will be prepared . . .

read more...

Building Construction and Renovation Update 8-11-2010

Footings have been recently been poured.  Two layers of concrete block will be installed around the perimeter of the building and the concrete slab will be poured.  Inside, the nurse's station and restroom have seen brick walls . . .

read more...

Groundbreaking Ceremony June 15

There will be a brief Groundbreaking Ceremony June 15 at 6:30 p.m. held at the new high school addition site.  This site is located on the southwest corner of the high school campus.  Board members, administrators, and . . .

read more...